Sep 1, 20232 minHigh Acres Landfill Operational Update 9/1/23Operations Update: Week of 8/28/2023 Daily Operations: The active working face is currently located in cells 11, 12 and 13. The working...
Aug 25, 20232 minHigh Acres Landfill Operational Update 8/25/23Operations Update: Week of 8/21/2023 Daily Operations: The active working face is currently located in cells 11, 12 and 13. The working...
Aug 18, 20232 minHigh Acres Landfill Operational Update 8/18/23Operations Update: Week of 8/14/2023 Daily Operations: The active working face is currently located in cells 11, 12 and 13. The working...
Aug 11, 20232 minHigh Acres Landfill Operational Update 8/11/23Operations Update: Week of 8/7/2023 Daily Operations: The active working face is currently located in cells 11, 12 and 13. The working...