top of page
Search

Gas Collection Update

During our daily gas field monitoring today, we located a cluster of 6 gas collection wells in the Cell 13 area that have a reduced vacuum source. These identified gas collection wells were determined to have an impacted vacuum line, that will need to be replaced.

We will be running these new vacuum lines from the recently constructed 12” sub header in this area. We have commenced work with our crew today and will be bringing in a contractor starting tomorrow to assist in this effort. This work will involve installing new vacuum lines to these impacted gas wells to increase gas capture in this area.

This work will be conducted as quickly as possible but will take approximately 2 weeks to complete( weather dependent). We will employ all practical odor control measures during this ongoing work.




Recent Posts

See All

Comments


bottom of page