High Acres Landfill Operational Updates- 7/8/2022

  • Jul 8, 2022
  • 1 min read

One of the powerplant engines compressor is currently down and the powerplant managers are actively trying to find a solution. All other engines are up and running normally as well as the flares to pick up the balance and manage the gas collection. Therefore, this maintenance will not impact gas collection or cause an increase in odors.





 
 
 

Recent Posts

See All
Cell 15 Construction Activity:

Over the next three to four weeks, we will be installing a 12-inch gas header at High Acres in Cell 15. This gas header construction consists of approximately 1350 LF of header pipe and multiple later

 
 
 