top of page
Search

High Acres Landfill Operational Updates 7/26/2024

Daily Operations:


The active working face is currently located in cells 11, 12 and 13. The working face is processing both rail and street volume and is utilizing clean soil, approved alternative daily cover and the Envirocover machine. The perimeter water/vapor-based neutralizer systems, and truck wash are also in operation.


NYSDEC Odor Hotline and Verification System: (585) 453-2416

A dedicated odor hotline and verification system for residents to report and record any concerns regarding High Acres Landfill and its operation.


Neutralizer Systems in use:




Daily Cover Enviro Cover Machine in use:




Construction Activities:


Temporary odors may occur during trenching and construction activities that are necessary for project completion and future improvements.


Cell 15A-1 – Q2 2024 excavation and structural fill complete.  The placement of geocomposite underdrain and clay are ongoing. The Riserhouse foundation and walls are set. Photo July 2024



East Perimeter Berm Construction – Started excavation and structural fill placement in early

May.  Approximately 130cy have been excavated to date.  Anticipate Fall completion.


photo July 2024




There is now a Stoplight at our haul road crossing on Quaker Road in the Town of Macedon and anticipated to last through Labor Day.




Renewable Energy Powerplant and Landfill Gas Management:


Continuous use of gas collection wells and flares for odor control. Ongoing work includes raising gas collection wells, installation of additional horizontal gas collectors, installation of gas vacuum lines, and upgrades to the gas collection wells for drainage and collection enhancement. Well-raising is a daily activity in coordination with filling operations.





WM has invested over $2.3 million in 2023 into the HALRC gas collection and control system. Most notably a new flare adjacent to Perinton Parkway was commissioned in November. This new flare will allow WM the flexibility to apply greater amounts of influence on the waste mass and destroy higher volumes of landfill gas. Technicians are working diligently to rebalance the field. Some instabilities are expected while this effort takes place. In addition, an upgrade to the LFG conveyance infrastructure has begun. This project will provide greater amounts of opportunity to expand the collection system in the future.







Current Events:


Price List for the Residential Drop-off Area





2023 WM Sustainability Report - WM is committed to consistent and meaningful public disclosure and discussion of our sustainability progress through the publication of our annual Sustainability Report. Read the PDF below to learn more.


(Aerial footage of the High Acres Sports Complex)




Please click the link below to access the Town's updates and news regarding WM High Acres Landfill and Recycling Center in the Town of Perinton.





Recent Posts

See All

Comments


bottom of page