Powerplant update 1/17/23Jan 17, 20231 min readAll Powerplant engines are back up and collecting at full capacity.
Cell 15 Construction Activity:Over the next three to four weeks, we will be installing a 12-inch gas header at High Acres in Cell 15. This gas header construction consists of approximately 1350 LF of header pipe and multiple later