Today's Construction Activity 11/19/24:

REMINDER TO RESIDENTS TO USE THE DEDICATED HOTLINE:


NYSDEC Odor Hotline and Verification System: (585) 453-2416

(A dedicated odor hotline and verification system for residents to report and record any concerns regarding High Acres Landfill and its operation.)


This morning at 5:10 a.m. we had a condensate pump failure in the Southside knockout at High Acres Site. This caused the Zink enclosed flare to shut down.

The site team responded immediately and restarted the flare at 6:30 A.M. only to have it go down again. The problem was diagnosed as a condensate pump failure and required a pump replacement. During the replacement of the pump, the Zink flare was down as well as some engines at both plants. The Zink flare and Powerplant were brought back online at 10:19A.M and all systems are running. The Parnel flare was fully operational during this down time period.