Update -10/22/22Oct 22, 20221 min read4 Powerplant engines are currently down and under repair till further notice.
Cell 15 Construction Activity:Over the next three to four weeks, we will be installing a 12-inch gas header at High Acres in Cell 15. This gas header construction consists of approximately 1350 LF of header pipe and multiple later